Building Set-Out Using String Lines & Profiles

1. Prepare the Site – Clear the ground and identify the building location.

2. Mark Reference Points – Set the first corner using a benchmark or survey point.

3. Install Profile Boards – Place profile boards outside the excavation area.

4. Stretch String Lines – Connect the profiles with string lines to outline the building.

5. Measure All Sides – Check that the length and width match the design drawing.

6. Check Diagonals – Measure both diagonals. If they are equal, the layout is square/rectangular.

7. Create 90° Corners – Use the 3-4-5 rule (or 6-8-10, 30-40-50 cm, 60-80-100 cm) to form accurate right angles.

8. Verify Dimensions – Recheck all measurements and corner positions.

9. Mark Foundation Lines – Transfer the string line positions onto the ground with lime, paint, or pegs.

10. Start Excavation – Begin foundation excavation only after the set-out is confirmed accurate.