Which of the following is not a test for measuring workability of concrete?
Anonymous Quiz
4%
a. Flow test
9%
b. Slump test
65%
c. Std consistency test
22%
d. Kelly ball test
The stone whose crushing strength is maximum, is:
Anonymous Quiz
71%
a. Granite
11%
b. Chalk
9%
c. Slate
9%
d. Marble
What is a Mullion in a window shutter?
Anonymous Quiz
65%
a. Vertical member running through shutter of window.
29%
b. Horizontal member of shutter.
4%
c.Inclined battening.
2%
d. None of these
❤3
Principles of planning for buildings include
a. Aspect and Prospect b. Roominess c. Grouping d. Flexibility and Privacy
a. Aspect and Prospect b. Roominess c. Grouping d. Flexibility and Privacy
Anonymous Quiz
8%
A. a and b only
12%
B. b and d only
6%
C. a and c only
73%
D. a, b, c and d
❤2
MACE Academy
f173bd86-3695-4de9-8e9f-08b5d56a363b_copy.pdf
Talathi post add in Group C form filling date extended
महाराष्ट्र नागरी सेवा राजपत्रित गट-अ व गट-ब संयुक्त पूर्व परीक्षा, महाराष्ट्र गट-ब (अराजपत्रित) सेवा पूर्व परीक्षा तसेच महाराष्ट्र गट-क सेवा पूर्व परीक्षा या वर्षातुन दोन किंवा अधिक वेळा घेण्याचा निर्णय स्थगित करण्याबाबत प्रसिद्धीपत्रक आयोगाच्या संकेतस्थळावर प्रसिद्ध करण्यात आले आहे.
Join : @macedhule
Join : @macedhule
❤1
The shortcoming of bar chart is
Anonymous Quiz
6%
a. lack of degree of details
16%
b. does not show progress of work
9%
c. activity inter-relationship
70%
d. All the above
❤2🏆2
Among the following, who is considered as the father of scientific management?
Anonymous Quiz
3%
a. Max. Weber
36%
b. Henry Fayol
56%
c. F.W Taylor
5%
d. Elton Mayo
❤2😱1
In what way does ABC analysis help the manager
Anonymous Quiz
17%
a. To purchase material at low price
33%
b. To exercise selective control
17%
c. To purchase material very fast
32%
d. To select good quality material
❤4
The optimistic time, pessimistic time and most likely time required for completion of activity is 4, 11 and 6 days respectively. The expected time is
Anonymous Quiz
7%
a. 5 days
33%
b. 6 days
22%
5.5 days
39%
d. 6.5 days
❤2
Consider the following statements:
(I) Critical path is longest path in network (II) Critical path is obtained by joining the event having zero or minimum slack. No state whether
(I) Critical path is longest path in network (II) Critical path is obtained by joining the event having zero or minimum slack. No state whether
Anonymous Quiz
52%
a. Both I & II true
16%
b. Both I & II false
18%
c. ( I ) true , II false
15%
d. ( I ) false ,( II ) true
❤4🔥1
Consider the following statements:
i. PERT is activity oriented network diagram ii. CPM is event oriented network diagram
i. PERT is activity oriented network diagram ii. CPM is event oriented network diagram
Anonymous Quiz
25%
a. Both i & ii true
17%
b.( i ) true ,( ii ) false
54%
c. Both i & ii false
4%
d. ( i ) False , ( ii ) true
❤2
What is the formula for Free float?
Anonymous Quiz
58%
a. F.F= Total float - slack at head
19%
b. FF = slack at head - Total float
19%
c. FF = Total float + slack at head
4%
d. None of these
🔥2❤1
Program Evaluation and Review Technique is used when
Anonymous Quiz
22%
a. Repetitive type of work exists
36%
b. Time estimation is uncertain
14%
c. Time estimation is very easy
28%
d. Cost optimization is of prime importance
❤3
At what change of price level is a revised estimate prepared ?
Anonymous Quiz
7%
a. 2 %
21%
b. 2.5
10%
c. 4 %
62%
d. 5%
❤2
Salvage value is defined as
Anonymous Quiz
21%
a. Value of dismantled materials of a property at the end of it's utility period
68%
b. Estimated value of a built up property at the end of it's useful life without being dismantled
5%
c. Value of the property shown in the account book in that particular year
5%
d. Present value of a property considering it to replaced at the current market rates
❤1
The unit of measurement for earthwork in surface excavation exceeding 1.5 m in width as well as 10 sqm on plan but not exceeding 30 cm in depth, is in
Anonymous Quiz
32%
a. Cu.m
55%
b. Sq.m
14%
c.10 sq.m
0%
d.Rmt
🔥1