Q:- You find out that contractor have carried out RT as the 10% contractual percentage required by the specification code. The specification also insists that an additional 2 weld, radiographed for every weld that is failed. One of the pipe's spools had an au acceptable defect which the contractor has ignored and radiographed another weld in its place which is acceptable, what would be your course of action be?